New Wixom Elementary

The new Wixom Elementary is located at 3515 West Maple Road in Wixom.
We're excited to have officially broken ground on the new Wixom Elementary on November 11, 2025. The new, state-of-the-art building is scheduled to open to our students in the Fall of 2027.
Resources
New Wixom Elementary Frequently Asked Questions

Are there considerations for the inclusion of a sidewalk along front of the new Wixom Elementary School?
The District has safety concerns about running a sidewalk in front of the new Wixom Elementary School. Current sidewalk plans are designed to deter students from walking across vehicle entrances and exits and to reduce the likelihood of students walking through the parking lot to reach the front door. However, the District has advised the City of Wixom that if the City provides written documentation requesting a sidewalk in front of the school, the District will accommodate the request.
What project information has the District shared with the City of Wixom?
The District has provided the City of Wixom all legally obligated information as well as additional supplemental information.
What is the status of the Wixom Elementary School site plan review with the City of Wixom?
Site plan approval is managed outside of the City’s jurisdiction.
What is the status of the Wixom Elementary School site plan approval with the State?
Two agencies have authority to approve the new Wixom Elementary School site plans–– the Bureau of Construction Codes (BCC) and the Bureau of Fire Services (BFS). Both agencies have given their final site plan approval and will continue to review the construction process, ensuring the District meets all State code requirements.
How is the District coordinating information requests with the City of Wixom?
The District is working with the City by sharing all legally required information, meeting regularly, and responding to additional questions.
Is the addition of a traffic signal in front of the subdivision on W. Maple Road under consideration?
Data from the District’s traffic study did not demonstrate that a traffic signal is necessary; however, the District has shared with the City that it is willing to discuss a traffic signal cost-sharing model.
Has the potential widening of W. Maple Road been considered as part of this project?
The District’s traffic study did not support widening W. Maple Road; however, the District has indicated a willingness to continue discussions with the City, including the possibility of widening the road through a cost sharing model.
Is an additional sidewalk connection to the east of the Wixom Elementary School property being considered?
The original plans did not include a sidewalk because there was no existing sidewalk to connect to. The District has indicated to the City of Wixom that it is willing to add an eastern sidewalk. Following further discussions, the City has committed to constructing the remaining section of sidewalk, connecting Wixom Road westward to the sidewalk on school property.
Have additional safety signs at the crosswalk been considered?
Both the District and the City of Wixom are committed to providing a safe crossing of W. Maple Road for the school community. The District has shared with the City of Wixom that it is willing to continue discussing a cost-sharing model.
What factors led to the decision to build a new Wixom Elementary School?
Constructed in 1949, the original Wixom Elementary now faces challenges related to traffic flow, safety, and aging infrastructure, along with higher maintenance and energy costs, and limited capacity to support modern technology. Investments in the existing building have helped provide a more equitable experience for Wixom students through the 2020–2027 period; however, constructing a new building represents a more sustainable and cost-effective long-term solution. Technology and furniture acquired through the previous bond will be repurposed in the new school.
Why is the existing elementary school being replaced?
The current building, originally constructed in the 1940s, has served the community for decades. Replacing it with a new facility allows the District to provide students and staff with a modern, safe, and efficient learning environment designed to meet today’s educational standards and future needs.\
What are the main benefits of the new school?
The new building will provide:
- Spaces designed for today’s teaching methodologies and future flexibility
- Improved safety and security systems
- Accessibility throughout the site and building
- Enhanced indoor air quality and energy efficiency
- Updated technology infrastructure
- Improved parking, traffic flow, and student drop-off/pickup areas
- Spaces that better support learning outcomes, collaboration, creativity, and student well-being
How will the new Wixom Elementary improve learning environments?
The new school is designed to create dynamic, student-centered learning environments. Classrooms will be flexible and filled with natural light, with excellent acoustics and adaptable furniture that can be easily reconfigured to support different teaching approaches. Dedicated areas for small-group learning, hands-on instruction, and technology integration will sit alongside larger collaboration zones, encouraging both focused work and teamwork.
These thoughtfully designed spaces promote student engagement and accommodate a wide range of learning styles–– supporting the idea that a happy, welcoming building helps nurture happy, motivated students. Exterior finishes have been selected to achieve a timeless yet playful aesthetic, while interior materials prioritize student well-being using sustainable, health-conscious design choices.
What does ADA accessibility mean, and how will the new school improve it?
ADA accessibility means the school will comply with the Americans with Disabilities Act, ensuring equal access for all students, staff, families, and visitors.
Improvements include:
- Step-free building entrances
- Elevators or accessible routes where needed
- Accessible restrooms and drinking fountains
- Wider corridors and doorways
- Improved parking spaces and pathways
How will parking and traffic circulation improve?
The new site design will significantly improve parking capacity and traffic flow by creating safer, more organized areas for:
- Parent drop-off and pick-up – designated queuing space for approximately 65 passenger vehicles on site – 50% more vehicles will be able to queue within the designated space than at the current building
- One location for drop-off and pick-up that does not split grade levels like at the current building in the afternoon
- School bus loading zones
- 40% more parking spaces than the current building
- Clear pedestrian walkways separated from vehicles
- Better site lighting and visibility
These improvements are intended to reduce congestion and enhance safety during busy arrival and dismissal times.
Will the new school be safer?
Yes. The new building will be designed with current safety standards in mind, including secure entrances, improved visibility, updated fire protection systems, emergency communication systems, and safer traffic circulation outside the building.
Will the school keep its community identity?
Yes. While the building is new, the goal is to honor the history and traditions of the school community while creating a facility that serves future generations of students.
What will happen to the old building?
The existing building will remain in use until the new facility is ready, minimizing disruption to students.
How will construction impact students and neighbors?
The District and project team are working to minimize disruptions by maintaining safe separation between construction and the road, communicating updates throughout the process.
Why invest in a new building instead of renovating the old one?
Older buildings often face limitations related to layout, safety, accessibility, aging systems, energy performance, and long-term maintenance costs. Building a replacement provides a more cost-effective, long-term solution while delivering a significantly better educational environment.
When will construction be completed?
The new Wixom Elementary will open in the fall of 2027.
How can the community stay informed?
Updates will be shared through District communications and board meetings.
Traffic Impact Study (TIS)
Traffic Study Documentation
- Wixom Elementary School Relocation Traffic Impact Study Review #2
- WLCSD Spalding DeDecker Traffic Impact Study - March 2026
- Operational Assessment Excerpt - March 2026
Traffic Impact Study Review
Hubbell, Roth & Clark, Inc. (HRC) has performed a review of the following items for the proposed Wixom Elementary School Relocation:
- Traffic Impact Study (TIS) by Spalding DeDecker & Associates (SDA) dated December 19, 2025
- Site Plan Response #1 Letter by SDA dated December 19, 2025
- City Review Plan Set by SDA dated December 19, 2025
The revised plan set shows the relocation of the Wixom Elementary School on Maple Road west of Wixom Road. The revised TIS includes traffic volumes, trip distribution, background growth, capacity analysis (existing, build, no-build, and build with improvements conditions), queuing analysis, turn lane analysis, and signal warrant analysis. HRC has the following traffic comments regarding the TIS, Response Letter, and Plan Set:
*Please Note - Critical items significantly impacting capacity and/or safety are highlighted in bold.
Data Collection
- The report still indicates the peak hours analyzed were 8:00 AM to 9:00 AM and 4:00 PM to 5:00 PM, but those times do not capture all the school-related traffic (especially the PM peak hour). The study should analyze the peak hour of the school (appears to start at 8:15 AM and 3:15 PM) and not the adjacent road.
- Comment not fully addressed from HRC Traffic Review #1
- Figure 2 shows the north driveway of the existing Wixom Elementary off Theodore west of Wixom Road, but Appendix D shows the driveway off Wixom Road south of Theodore. The driveways shown in Figure 2 and Appendix D should be consistent.
Trip Distribution
- Table 1 shows the inbound trip distribution percentage from the east is 34% during the PM peak, but that estimate seems extremely high considering that direction is limited to staff and school of choice. That percentage is also higher than the estimate coming from the south (19%), which does not seem practical. The trip distribution percentage from the east should be revised or provide further evidence to substantiate this claim.
- Table 2 shows the trips from the existing elementary school, but it is unclear how these numbers were determined. The existing trips also seem low (especially PM inbound). The sum of volumes at Theodore, North Drive, and South Drive during the peak hours of the school (see Item 1) should reflect the trip generation for the school. Furthermore, the principal has indicated approximately 200 passes have been issued to allow parents to pick up their child. The report should clarify how the trips for the existing elementary school were determined.
- Comment not fully addressed from HRC Traffic Review #1
Analysis Scenarios
- The report indicates the peak times analyzed refer to the school rather than the street, but the volume counts do not reflect that. The volumes highlighted in the turning movement count sheets reflect the peak hour of the street. The study should analyze the peak hour of the school (see Item 1).
- The report includes various scenarios, but there are volume discrepancies between the turning movement count sheets, volume diagrams (Appendix D), and models between conditions (existing, no-build, build) at the following locations.
- Southbound Castlewood at Maple for Existing Condition (AM and PM peaks)
- Northbound Wixom at Maple for Existing Condition (AM peak)
- Southbound Wixom at North School Drive for 2027 Build Condition (PM peak)
- Southbound Wixom at South School Drive for 2027 No-Build Condition (AM peak)
- Southbound Wixom at South School Drive for 2047 No-Build Condition (PM peak)
- Northbound Wixom at Theodore for 2047 No-Build Condition (AM peak)
- The existing, no-build, and build volumes should be consistent starting from the turning movement count sheets.
- Figures C-4 and C-9 show the development volumes shaded in pink, but the trip assignment is not balanced throughout the road network. The trip assignment should be balanced throughout the road network.
Roadway Geometry
- The report still indicates Wixom Road transitions to a divided roadway north of Maple Road, but it does not have a median. The report should remove the statement of transitioning to a divided roadway.
- Comment not fully addressed from HRC Traffic Review #1
Proposed Levels of Service
- Tables 16 – 23 show the level of service (LOS) and queue length for the buildout from the modeling, but the results are flawed since it did not account for any adjustments in heavy vehicle (buses) percentage or peak hour factor (traffic flow). The shift in traffic from the existing to the proposed school will increase the turning movements for buses to and from Maple Road. The shift will also cause the traffic flow to spike during drop-off and pickup times rather than having a constant flow during the hour as the models currently show. The models should increase the heavy vehicle percentage to 10% and decrease the PHF to 0.60 for school-related movements to reflect actual conditions.
Turn Lane Treatment Analysis
- The report indicates volumes remain slightly under the threshold to recommend a left-turn treatment on westbound Maple at the driveways, but the outcome may change when the peak hour of the school is analyzed (see Item 1). There is also concern that the trip generation is too low (see Item 4). The left-turn lane analysis should be redone to include volumes from the peak hour of the school and updated trip generation.
- Table 26 shows to retain the existing passing flare on eastbound Maple Road and the West Driveway, but the location is no longer a T-intersection. Passing flares should not be used at four-leg (traditional) intersections since they create sight distance issues for opposing (westbound) left-turns. The passing flare also encourages a dangerous free-flow movement through a proposed crossing and creates another conflict point for students. The taper on the downstream side (east of driveway) should be removed to restrict passing vehicles and shorten the crossing distance (see attached). However, the taper on upstream side (west of driveway) can be retained to serve as a right-turn treatment.
Report Overview
- The report indicates a northbound right-turn lane was modeled to improve congestion, but it is unclear if the school is including this with their project. The report also indicates an added northbound lane was modeled and resulted in an improvement. The report should clearly indicate what improvements are recommended and being picked up by the School Project.
- Comment not fully addressed from HRC Traffic Review #1
Site Plan
- The site plans should include a turning path sheet showing the movement of a fire truck navigating the site to verify that the radii are large enough to accommodate all turns. A truck circulation plan for all large vehicles anticipated at the site is required per the City of Wixom’s Ordinances 18.15.040 and 18.17.030. The radius and median at the East Drive entrance also has the geometry of a right-in only access possibly making it difficult for fire trucks. The turning paths for fire trucks circulating the site should also be shown and approved by fire safety to verify they can access all critical areas (spigots).
- Comment not fully addressed from HRC Traffic Review #1
- The site plans should include a drop-off and pickup circulation plan clearly showing the internal traffic flow pattern and number of standing vehicles the site is able to hold without spilling back onto Maple Road.
- Comment not fully addressed from HRC Traffic Review #1
- Sheet C6.0 shows a crossing on Maple Road east of the West Drive, but there is no traffic control (signal) to create gaps for students to cross. The crosswalk is also located right into a turning movement of a bus exiting the driveway, passing flare (see Item 11), and westbound right-turn lane. Consideration should be given to shifting the crossing away from the West Drive and adding a pedestrian-actuated signal to provide students with a regulated crossing.
- Comment not fully addressed from HRC Traffic Review #1
- Sheet C6.0 shows various sidewalks within the property, but they stop near the right-of-way. There is a neighborhood east of the school that may attract students. Sidewalk should be added on the north side between the West Drive and Maplewood.
- The site plans should include School signs (S1-1) with AHEAD plaques (W16-9P) on Maple Road to advise road users they are approaching a school.
HRC has reviewed the TIS, City Review Plan Set, and Response Letter with the above traffic exceptions noted. There is still concern that the redistribution of school traffic will have a significant negative impact on Maple Road. Residents north of the school are still expected to have a challenge navigating the surrounding area during drop-off and pickup times. The short eastbound left-turn lane storage on Maple Road at Wixom Road is also still concerning and may cause spillback beyond the diverging point (taper). The report also has not provided any evidence that the parking lot can accommodate all drop-off and pickup vehicles without having them spill back onto Maple Road (see Item 14). Adding a left-turn lane throughout the corridor helps mitigate these concerns. A left-turn lane also provides a de facto turnout space for standing (drop-off and pickup) vehicles to move out of the through lane if they spill out of the parking lot. From a traffic standpoint only, HRC does not find the TIS and site plan to be acceptable. Resubmittal of the TIS and City Review Plan Set should
be performed addressing the items above.
Wixom Elementary Site Plan
The new Wixom Elementary will be a state-of-the-art facility built with improved storm water management measures, right of way improvements and traffic safety devices.
The current site plan features three playground areas for students and a soccer field. Inside will also feature collaboration spaced for staff and students, as well as enhanced learning spaces for students to thrive.